Hello, Mr. Sharma
badge
Project ID: AN-2023-884
• location_onPlot 45, Green Valley
Project Status
65%
Complete
Current Phase
Phase 3: Structural Framework
The structural framework is well underway. First floor slab casting is scheduled for next week.
Last Update
calendar_today
Oct 24, 2023
Est. Completion
flag
Mar 15, 2024
Recent Milestones
check
Foundation Completed
Oct 24All foundational concrete work and curing has been certified by the site engineer.
construction
Structure Framework
In ProgressErection of pillars and beams for the ground floor.
radio_button_unchecked
First Floor Slab
UpcomingScheduled to begin after structural inspection.
Quick Actions
photo_camera
View Photos
account_balance_wallet
Track Payments
Mrs. Alisha
Contact Architect
folder_open
Documents
Need Assistance?
Your site manager is available for a call.
Rajiv Malhotra
Site Manager